"This is due to the use of high-tech materials in the manufacture of the reaction pipes themselves and the involvement of highly qualified personnel to their welding, installation and quality control of work performed," the company explained.
Start-up and adjustment works are actively carried out in the compressor unit building, where all technological equipment is already installed. Is setup and running-in lubrication and cooling systems, performed commissioning of control systems for compressors, electrical systems, and checking the work of locks.
"Construction of a hydrogen production complex N-Оіl homestretch" - summed up in the company.
The complex of hydrocracking of heavy oil residues at the Mozyr refinery includes a combined hydrocracking unit, hydrogen production and sulfur production units, 21 objects of the General plant economy. The implementation of the investment project will increase the yield of light, more expensive and marketable oil products up to 70% and ensure the depth of oil refining up to 90%. The projected cost is more than $1.2 billion.
Mozyr oil refinery was commissioned in 1975, at JSC are converted in 1994. In the authorized Fund the share of the State property Committee of Belarus is 42,76%, JSC "NGK "Slavneft" - 42,58%, OOO "MNPZ plus" - 12,25%, private persons - 2,41%. The main activities of the plant: oil refining, production and sale of petroleum products.